What compensation can be claimed for goods damaged in transit?
On a road haulage contract within Spain, the carrier is liable for the loss of and damage to the goods from the moment it receives them until it delivers them. It must refund the corresponding part of the price of the carriage and pay what the goods were worth or the value they have lost, although it does not pay more than 6,67 euros per kilo for the goods, which in 2026 is the statutory limit of one third of the daily “IPREM”, Spain's public income indicator. In international carriage the CMR Convention applies, with a limit of 8,33 special drawing rights per kilo. The damage must be noted in writing on receipt of the goods or, if it was not visible, within the following seven days. The claim becomes time-barred after one year.
Alburquerque Abogados
What you can claim
The “Ley del Contrato de Transporte Terrestre de Mercancías”, Spain's act on the contract for the carriage of goods by land, makes the carrier (“porteador”) liable for the loss of and damage to the goods while they are in its hands. The compensation covers the following:
- If the goods are lost, their value at the time and place where the carrier received them, normally the market price.
- If they arrive damaged, the amount by which they have lost value, without exceeding what would be paid for their loss.
- In both cases, the price of the carriage and the other expenses it has caused, in full if the loss or damage is total and in proportion if it is partial.
Beyond that, the law does not in principle allow other losses to be claimed from the carrier, such as lost sales. The carrier is released if it proves that the damage was due to the person who loaded or received the goods, to a defect in the goods themselves or in their packaging, or to circumstances it could not avoid.
The limit per kilo
What is paid for goods that are lost or damaged cannot exceed one third of the daily “IPREM”, Spain's public income indicator, for each kilo of their gross weight. The IPREM, which is set by the budget law, is 20 euros a day in 2026, so the cap is 6,67 euros per kilo. For a 200-kilo machine worth 30.000 euros, the carrier would pay at most about 1.333 euros, in addition to the price of the carriage.
This limit cannot be lowered by contract. It is exceeded if the value of the goods was declared when the contract was made, or a higher limit was agreed in return for a supplement to the price, or if the damage was caused by wilful misconduct or by a conscious and deliberate breach of the carrier's duties. In all other cases the carrier does not pay the difference, which it is advisable to cover with cargo insurance.
In international carriage by road the CMR Convention (the Convention on the Contract for the International Carriage of Goods by Road) applies. Its limit is 8,33 special drawing rights per kilo, a unit of account of the International Monetary Fund whose value in euros changes every day.
Reservations and time limits
The time limits to watch are these:
- If the damage or shortfall is visible, the reservation must be made in writing on receipt of the goods, for example on the delivery note.
- If it is not visible, the written reservation must be sent to the carrier within seven calendar days of delivery. Under the CMR Convention it is seven days not counting Sundays and public holidays.
- The claim becomes time-barred after one year, counted in general from delivery. Where there is wilful misconduct, the period is two years and, under the CMR Convention, three.
Without a reservation it is presumed that the goods arrived in the condition in which they were loaded. The person claiming has to prove otherwise. A written claim to the carrier suspends the limitation period until the carrier rejects it in writing. Delay in delivery is compensated only up to the price of the carriage, provided that a written reservation is made within twenty-one days.
Claims of up to 15.000 euros are deemed to be subject to arbitration by the “Junta Arbitral del Transporte”, the transport arbitration board, unless one of the parties excluded it before the carriage began. To go to court, the law generally requires an attempt to reach an agreement before suing.
This answer is provided for educational purposes and offers initial guidance on the question raised. Every matter has its own circumstances and nuances that require individual assessment. For that reason, before taking decisions with significant consequences, it is advisable to consult a professional and not to rely solely on this information. Personalised advice makes it possible to apply these explanations to the specific case and to assess the options available with greater certainty.